What is the schedule for construction activities?

Site preparation work began in April of 2022 during the spring school vacation. This work will continue until the end of this school year and will include:

  • Perimeter fence and scrim installation;
  • Development of the construction entrance drive at Beacon Street – will include curbing re-work, excavation, tree root removal, grading, asphalt and sidewalk transition;
  • Pruning, clearing and grubbing within the construction site;
  • Creation of a site access road within the construction fenced area;
  • Removal of existing structures within the construction area – play structures, backstops, etc.

Immediately following the end of the school year in June 2022, full construction activities will begin.

Show All Answers

1. What will the new West El/Shawsheen Preschool look like and where will it be located?
2. How will the educational environment be improved at the new West El?
3. How will the educational environment be improved at the new Shawsheen preschool?
4. What is the schedule for construction activities?
5. How will traffic circulation change during construction?
6. How will construction vehicles enter and exit the site?
7. How will people be notified of changes in traffic circulation?
8. What will the project work hours be?
9. Will play areas be relocated during construction?
10. What will happen to the playing fields behind the current West El?
11. Will there be other impacts on students’ learning environment during construction?
12. When will the new schools open?
13. What are the next steps in the MSBA process/timeline?
14. What is the project budget and what is being done to ensure that there are no cost overruns?
15. What will the tax impact be of the new West El/Shawsheen Preschool?
16. Will the project involve redistricting and, if so, when will that occur?
17. The new WESB project is described as “Net Zero Ready.” What does that mean?
18. Why wasn’t the installation of solar panels on the roof and/or in the parking areas made a part of the current construction project?
19. How much of the new West El/ Shawsheen Preschool energy needs will come from on-site sources?
20. What will happen to the existing West El facility?
21. What will happen to the existing Shawsheen facility?
22. Who are the project contractors?
23. Who serves on the West Elementary/Shawsheen School Building Committee?
24. How can I get more information about the project?